Updated RTS Link Ridership Forecast, Causeway Crossing Reduction and Safety Reasons for Certification Delays
4 November 2026
Written Reply to Parliamentary Question
Mr Jackson Lam asked the Minister for Transport with the Johor Bahru-Singapore Rapid Transit System (RTS) Link opening now expected in February 2027
a. what is the Land Transport Authority's updated forecast of daily ridership;
b. how much are Causeway car and bus crossings expected to fall; and
c. what outstanding safety certification items have caused the delay.
Reply by Minister for Transport Jeffrey Siow
1. The Johor Bahru-Singapore Rapid Transit System (RTS) Link will have a maximum capacity of 10,000 passengers per hour in each direction. Earlier studies indicated that it could alleviate Causeway traffic considerably when it opens. However, the utilisation and impact will depend on factors such as shifts in commuter travel patterns and the fares set by the operator.
2. As announced on 2 October 2026, RTS Operations Pte Ltd (RTSO) is currently carrying out its system tests and trial runs. RTSO will subsequently obtain safety certification from an independent safety assessor, before regulatory approval can be granted by authorities from both countries after review.