Written Reply by Minister for Transport Ong Ye Kung to Parliamentary Question on Assessment of Structural Integrity of Building at 68-74 Thomson Road
10 May 2021
This article has been migrated from an earlier version of the site and may display formatting inconsistencies.
Ms Poh Li San asked the Minister for Transport
a. whether a thorough assessment of the structural integrity of the building at 68-74 Thomson Road to withstand the construction of the North South Corridor (NSC) could have been made so that its owners and occupants need not have to move out temporarily and then be told later of the need for demolition; and
b. whether the alignment of the NSC can be adjusted further away to avoid the need to demolish the building.
Reply by Minister for Transport Ong Ye Kung:
1. A thorough impact assessment study of 68-74 Thomson Road (“the Building”) was conducted in early 2020. Inspections and non-invasive tests, in accordance with international practices and guidelines, were conducted. The study found that the Building’s foundation would need to be strengthened to withstand the excavation works for the North-South Corridor (NSC) tunnel, and therefore demolition was not required. To ensure safety during the strengthening works, the Land Transport Authority (LTA) assisted the occupants to move out of the Building.
2. However, after the residents had vacated the premises, LTA, as part of its due diligence, conducted further detailed and invasive tests to validate the Building’s concrete strength. It was through these tests that LTA found that the actual concrete strength was lower than required to safely carry out the strengthening works. This test would not have been part of the first test, which was to ascertain if the building foundation requires strengthening in view of the excavation works of the NSC. The Building and Construction Authority concurred with the test results and assessment. The Government therefore decided that for safety reasons, the Building has to be demolished before excavation works for the NSC tunnel near the Building can commence.
3. The NSC alignment was announced in 2011 after an extensive study by agencies, and takes into account the fact that the Thomson area is very densely built up with buildings next to the road reserve and underground MRT tracks in the vicinity. Due to site constraints, the two NSC tunnels (one tunnel for each direction of traffic flow) are already designed to be vertically stacked, instead of being built side by side, under the road reserve of Thomson Road. Given these land constraints, it is not possible to adjust the NSC alignment to avoid affecting the Building or other buildings along Thomson Road.
