Written Reply to Parliamentary Question on Implementation Timeline and Order of Roll-Out for Two-Carriage Trains for Sengkang-Punggol LRT
22 September 2025
This article has been migrated from an earlier version of the site and may display formatting inconsistencies.
Asoc Prof Jamus Jerome Lim asked the Acting Minister for Transport regarding the 25 new two-carriage trains ordered for the Sengkang-Punggol LRT
a. what is the detailed timeline for implementation on both loops in Sengkang and in Punggol; and
b. what factors determine the order of rollout across these service areas.
Reply by Acting Minister for Transport Jeffrey Siow:
1. We are on track to fully deploy the new two-car Light Rail Vehicles (LRVs) for the Sengkang-Punggol LRT (SPLRT) by end-2028. Two LRVs have already been deployed, and the remaining LRVs will be deployed across the SPLRT based on operational requirements and prevailing passenger loading conditions as they arrive.